More than once you are faced with a major loss of time when repairing this apartment and premises – this happened that at the very beginning of the work all the necessary technological and normative processes were not taken into account, and there was no distinct work plan. If you are interested in the repair of apartments of the wall decoration, we advise you to follow the link.
As an example, one small case can be given from your own practice, the one that will move back the deadlines for more than one month. The walls and ceilings of this room are already ready for painting and gluing with wallpaper. And here suddenly the owner of this premises decides to unexpectedly install the floors not on the lags, but to pour a small screed. The layer is naturally decent, and it will gain the fortress and it will dry out at least 20 days later. All work after the filling was suspended for this period.
Having given this example, I wanted you to realize where it was necessary to start repairs. Later, the screed filling in a maximum of three – four days will gain the desired fortress and will be allowed to walk on it and engage in other work, and let it dry further.
Thick layers of plaster should dry well. If you do not let it dry, but immediately put it, paint or stick wallpaper, then mold and a large fungus under and on them, you are guaranteed one hundred percent.